top of page

Can Jurisdiction Depend on How the Dispute Is Characterised?

Writer: Aişe Gül Akkoyun
Aişe Gül Akkoyun
Aug 24
2 min read

If a shipbuilder and a government disagree about a broken contract, can they even agree on where to argue about it? A dispute over two patrol vessels for Uruguay's navy

Background

Cardama, a Spanish shipbuilder, contracted to build two offshore patrol vessels for Uruguay's navy. When the relationship broke down, each side pointed to a different reason and, more importantly, a different forum. Cardama filed an ICC arbitration in Paris, pointing to a clause in the contract covering technical disagreements left unresolved by the classification society Lloyd's Register. Uruguay contests that framing, arguing that what actually happened was a non-technical breach involving a false guarantee and a defective reimbursement instrument, which in its view belongs before a Montevideo court rather than an arbitral tribunal.

A contract that points two ways

The dispute turns on a single interpretive question: which clause governs? Cardama reads the contract's technical dispute mechanism as broad enough to cover the entire falling-out, since the underlying disagreement traces back to inspection and classification issues that Lloyd's Register never resolved. Uruguay reads the same contract narrowly, arguing that a guarantee instrument and a reimbursement mechanism sit outside that clause entirely, and that disputes over them were never carved out for arbitration in the first place. Whether the same set of facts can be sliced into an arbitrable technical dispute and a non-arbitrable contractual one is, in effect, the whole case.

Two accounts of the same termination

Cardama's version centres on the vessels themselves: technical shortcomings that Lloyd's Register was supposed to certify or resolve, and never did, leaving the shipbuilder unable to deliver a compliant product on the agreed terms. Uruguay's version centres on the paperwork behind the deal: a guarantee it says was misrepresented, and a reimbursement instrument it says was defective from the outset, which together go to the validity of the contractual relationship rather than to any single vessel's specifications. Two governments, or in this case a government and a shipbuilder, can watch the same contract collapse and locate the cause in entirely different places.

Parallel proceedings, meanwhile

Uruguay has signalled it intends to pursue its own claims before a Montevideo court, which raises the prospect of two proceedings running side by side over the same underlying relationship: an ICC tribunal in Paris asking whether the technical dispute clause covers the disagreement, and a domestic court asking whether the guarantee and reimbursement issues belong to it instead. This is not a new problem in shipbuilding disputes. In BAE Systems v. Trinidad and Tobago, a similarly cancelled patrol vessel contract produced its own ICC arbitration after a change of government scrapped the deal, underscoring how naval procurement contracts, expensive, politically exposed and technically complex, keep producing exactly this kind of jurisdictional standoff.

If a contract can be sliced into a technical dispute and a contractual one, and each half sent to a different forum, what actually stops a party from choosing its characterisation of a dispute in order to choose its judge?



Comments


bottom of page